December 8 Update

As of December 8, the following items have been completed:

Foundation construction, 95% of waterproofing, installation of stones, elevator tower construction, beginning of exterior / interior drain work, steel shop drawings for final review, (Note: Once the drawings are approved by the architect, steels can be ordered. Steel will be fabricated in the shop which can take a long time as our builder does not have control over their schedule. For this reason the builder will not give us an estimated completion date until the steels are installed.), stair shop drawings for initial review.

Work to be done in the upcoming days or weeks:

a. Complete interior and exterior drains in a couple of weeks.

b. Partial backfill of basement.

c. Excavation for steps / ramps / porch footings.

d. Elevator shop drawings for final review.

e. Duct drawings for review.

f. Re-submit sprinkler system drawing to the fire sub code department for review and approval. Obtaining the building permit is predicated on the approval of sprinkler system from the fire sub code department.